5.1 preparation: before starting the machine, first check whether there are materials, sundries and jamming in the crushing chamber; before
starting the machine every day, check whether all fasteners are completely fastened, and deal with them immediately if they are loose; check
the lubrication of each rotating part before starting the machine
5.2 start up: the machine and transmission parts can be started up only after the inspection proves that they are in normal condition; the
machine must only be started under no load, otherwise it is easy to damage the motor, reducer, coupling, etc; start (jog the test run first) if
there is any abnormal condition or abnormal sound, stop the start immediately, find out the cause and eliminate the fault before starting again
5.3machine operation: When the machine is running, the maintenance personnel should often go to the side of the machine to observe the operation: whether the
machine has abnormal sound. If it occurs, first determine the position, and then stop the machine for inspection and treatment; whether the
temperature rise of the motor is too high. Under normal conditions, the maximum temperature shall not exceed 80 ºC; check whether the bolts
at the rotating part are loose. If they are loose, stop the machine immediately.
5.4shut dowu: Before the machine stops working normally, the feeding shall be stopped first, and the crusher can be stopped only after all materials in the
standby are broken. In case of machine failure or dangerous situation, the power supply can be cut off immediately.
4.Specifications and technical parameters of double shaft shredder: